RABIGH CEMENT PLANT EXPANSION

Rabigh Cement Plant Expansion

GAMA performed construction of a new clinker production line with a capacity of 7,000 tons/day starting from and including the new limestone crusher up to and including the packing and bulk loading plant as well as construction work for new power plant and connection to existing lines.

Yamama Cement Plant – Line No.7

GAMA Industry performed turnkey construction of Yamama Cement Production Line No.7 with 10,000 tonnes/day clinker capacity at the existing cement plant facilities, within the scope of “Sales & Purchase Contract” and “Construction & Erection Contract”, including the construction of a new cement mill unit for the existing Line No.6 .

At the time, world’s biggest cement plant; Yamama Cement Plant is executed by GAMA Industry Arabia Ltd.

QNCC Cement Plant Line No.3

Mechanical, electrical and instrumentation erection works of a new 4,000 ton per day capacity clinker production line.

EPCC Cement Plant New Clinker Production Line

Construction of the 3,500 ton per day capacity New Clinker Production Line No.3, including raw material and meal preparation and storage, preheater and clinker production, clinker cooling, clinker storage, raw meal and clinker dedusting, heat recovery and transportation systems is implemented.

This project is executed by GAMA Industry Arabia Ltd.

Hereke Cement Plant

Design, construction, manufacturing and complete mechanical and electrical erection of 1 ea. complete crushing unit, 1,500 t/hr capacity 1 ea. complete pre-homogenising unit; 50,000 ton storing, 1,800 t/hr stacking and 800 t/hr reclaiming capacity 1 ea.

Unye Cement Plant

GAMA Industry performed construction and erection works to increase the production capacity from 1,800 tons/day to 4,500 tons/day by precalcination.

 

Bursa Cement Plant

Design, construction, manufacturing and complete mechanical and electrical erection of kiln precalcination unit.

Kedah Cement Plant

GAMA Industry executed Line No. 2 Plant Expansion Project consisting of 6,000 tons/day portland cement production line and associated systems.

Denizli Cement Plant

GAMA Industry executed construction, manufacturing and erection of Precalcination Unit.

Ankara Cement Plant

GAMA Industry performed construction and erection of 1,500 ton/day capacity clinker production line as an extension to the existing factory, including crushing plant, raw materials grinding plant, preheater, kiln, dedusting unit and other associated systems including power supply system.