150 MW Kirikkale Diesel Power Plant
Based on PPA, the project is a fully privately financed and constructed on turn-key basis with two significant phases:
- Construction of 150 MW (established capacity) combined cycle diesel power plant (consist of 13 each 11 MW engines and one 9.5 MW steam turbune & generator),
- Operation of the power plant for 5 years with 8,760 hr/year and 130 MW-100% availability.
EPC contract includes all basic & detailed design of the power plant, procurement of all power plant equipment, all civil, structural works, all mechanical erection works, installation of all electrical, instrumentation and control systems. The contract also includes commissioning, start-up works and training of client’s personnel.
Operation of the plant is also in the scope of GAMA.