16.5 MW CAKIRLAR RUN OF RIVER HYDROELECTRIC POWER PLANT

16.5 MW Cakirlar Run of River Hydroelectric Power Plant

GAMA Renewable Energy Systems Construction Co. (GAYES), a subsidiary of GAMA, executed the project as the enginering, procurement and construction contractor.

With the altitude of 1,400 m – 930 m, run of the river type hydroelectric power plant project has 2×8.25 MW pelton turbines. Electromechanical equipments are provided by VAtech – STE – Indar Consortium on a turn-key basis.

Power Plant is delivered to the Owner with fully operational condition. In addition, GAMA Renewable Energy Systems assisted & managed relations with public & state authorities for the permits and licences on behalf of the Owner/Investor during the construction period.

Location Icon
Location
Murgul, Artvin, Turkey
Client Icon
Client
Anadolu Elektrik Üretim A.Ş. (a subsidiary of GAMA Enerji)
Contractor Icon
Contractor
GAYES (GAMA Renewable Energy Systems Construction Co.)
Duration Icon
Project Duration
26 Months (May 2007 - August 2009)