16.5 MW Cakirlar Run of River Hydroelectric Power Plant
GAMA Renewable Energy Systems Construction Co. (GAYES), a subsidiary of GAMA, executed the project as the enginering, procurement and construction contractor.
With the altitude of 1,400 m – 930 m, run of the river type hydroelectric power plant project has 2×8.25 MW pelton turbines. Electromechanical equipments are provided by VAtech – STE – Indar Consortium on a turn-key basis.
Power Plant is delivered to the Owner with fully operational condition. In addition, GAMA Renewable Energy Systems assisted & managed relations with public & state authorities for the permits and licences on behalf of the Owner/Investor during the construction period.