2×39.5 MW ERDEMIR COGENERATION POWER PLANT

2×39.5 MW Erdemir Cogeneration Power Plant

Turnkey design, supply and construction of a natural gas fired cogeneration plant, comprising two GE frame 6B gas turbine generators (39.5 MW capacity each) and two HRSG’s (each generating 80 tons/hr of medium pressure and 4 tons/hr of low pressure steam), including all auxiliary components are executed.

Location Icon
Location
Eregli, Turkey
Client Icon
Client
Eregli Demir ve Celik Fabrikalari A.S. (Erdemir) / Turkey
Contractor Icon
Contractor
Consortium of ELIN Energieversorgung (Austria), Babcock and Wilcox, GAMA (BWG) (Turkey)
Duration Icon
Project Duration
First Unit: 14 Months (April 1996 - June 1997) • Second Unit: 16 Months (April 1996 - August 1997)