AIN-GHAZAL WASTE WATER IMMEDIATE RELIEF PIPELINE

Ain-Ghazal Waste Water Immediate Relief Pipeline

Turnkey construction of a Waste Water Treatment Plant including sewage decomposing unit, 220 hectares of waste stabilisation and emergency ponds, 40 km long 50” diameter pipeline including cathodic protection, 4 km long access roads, waste collection and pretreatment system, odour control system, 110 kg/hr automatic chlorination system and maintenance facilities.

Location Icon
Location
Amman, Jordan
Client Icon
Client
Water Authority of Jordan
Contractor Icon
Contractor
GAMA Industry Inc.
Duration Icon
Project Duration
39 Months (May 1983 - August 1986)