ATYRAU REFINERY RECONSTRUCTION

Atyrau Refinery Reconstruction

Construction of additional units (gasoline, diesel, sulfur, hydrogen, coker) and renovation works for the Atyrau Refinery is implemented.

Civil construction works, structural steel works, mechanical works, piping works, electric and instrumentation works, insulation, painting and fire proofing works are performed by GATE (a subsidiary of GAMA with %50 share) as subcontractor to JGC.

Location Icon
Location
Atyrau, Kazakhstan
Client Icon
Client
Kasmunaigas / Kazakhstan
Contractor Icon
Contractor
JGC - Japan
Duration Icon
Project Duration
23 Months (January 2004 - November 2005)