Petrokemya Polyethylene Plant, Saudi Arabia

Petrokemya Polyethylene Plant

GAMA Industry performed Engineering-Procurement-Construction of 4 industrial buildings with a total volume of 29,149 cubic meters and execution of complete civil and mechanical installation works for construction of new Polyethylene Plant having a production capacity of 800 KTA.

Location Icon
Location

Jubail, Saudi Arabia

Client Icon
Client

Petrokemya - Arabian Petrochemical Company

Contractor Icon
Contractor

SATEC - Saudi Toyo Engineering Company

Duration Icon
Project Duration

22.5 Months (October 2001 - December 2003)

Prizes Icon
Award
                    Array
(
    [0] => 11 Million Man-Hours w/o LTI  (project total)
)