Rabigh Cement Plant Expansion, Saudi Arabia

Rabigh Cement Plant Expansion

GAMA performed construction of a new clinker production line with a capacity of 7,000 tons/day starting from and including the new limestone crusher up to and including the packing and bulk loading plant as well as construction work for new power plant and connection to existing lines.

Location Icon
Location

Rabigh, Saudi Arabia

Client Icon
Client

Arabian Cement Company

Contractor Icon
Contractor

GAMA

Duration Icon
Project Duration

35 Months (November 2005 - October 2008)

Price Icon
Project Amount

137 Million USD

Man Hour Icon
Man-Hour

6 Million Man-Hours