SAKHALIN-II LNG PLANT

Sakhalin-II LNG Plant

Sakhalin-II LNG Plant offsite, utility, OET piping and steel erection works are implemented.

 

Location Icon
Location
Sakhalin, Russian Federation
Client Icon
Client
Sakhalin Energy Investment Company (SEIC)
Contractor Icon
Contractor
CTSD Ltd. (Chiyoda – Toyo Consortium, Japan)
Duration Icon
Project Duration
44 Months (April 2004 - November 2007)
Price Icon
Project Amount
65 Million USD (GAMA portion)
Man Hour Icon
Man-Hour
3 Million Man-Hours