2×660 MW ISKENDERUN SUGOZU COAL FIRED POWER PLANT

2×660 MW Iskenderun Sugozu Coal Fired Power Plant

The project consists of turn-key construction of two units of imported coal fired steam boilers and turbine generator sets with a total capacity of 1320 MW electric power (2×660 MW) including coal handling system, flue gas desulphurization plant, sea water cooling handling system, coal unloading jetty, stack and other auxiliary units.

GAMA – Tekfen Joint Venture was responsible for the construction of the plant, including the coal unloading jetty.

Hereke Cement Plant

Design, construction, manufacturing and complete mechanical and electrical erection of 1 ea. complete crushing unit, 1,500 t/hr capacity 1 ea. complete pre-homogenising unit; 50,000 ton storing, 1,800 t/hr stacking and 800 t/hr reclaiming capacity 1 ea.

3×210 MW Kemerkoy Thermal Power Plant Flue Gas Desulphurisation Plant

GAMA Industry performed turnkey construction of Flue Gas Desulphurisation Plant with wet limestone process for 3×210 MW Kemerköy Thermal Power Plant Units I, II & III, consisting of Limestone Handling, Absorbent Preparation, Scrubbing (with 3 ea. Scrubbers), Flue Gas, Gypsum Dewatering & Handling, Utility, Electrical and C&I Systems, including infrastructure and buildings.

Qatar Embassy and Ambassador Residence

GAMA Industry performed turnkey supply and construction of embassy, ambassador redidence, visa section and guard houses, landscaping and infrastructural works.

Construction area: 6,452 m2 closed building area + 9,263 m2 outdoor area

Unye Cement Plant

GAMA Industry performed construction and erection works to increase the production capacity from 1,800 tons/day to 4,500 tons/day by precalcination.

 

150 MW Kirikkale Diesel Power Plant

Based on PPA, the project is a fully privately financed and constructed on turn-key basis with two significant phases:

  1. Construction of 150 MW (established capacity) combined cycle diesel power plant (consist of 13 each 11 MW engines and one 9.5 MW steam turbune & generator),
  2. Operation of the power plant for 5 years with 8,760 hr/year and 130 MW-100% availability.

EPC contract includes all basic & detailed design of the power plant, procurement of all power plant equipment, all civil, structural works, all mechanical erection works, installation of all electrical, instrumentation and control systems. The contract also includes commissioning, start-up works and training of client’s personnel.

Operation of the plant is also in the scope of GAMA.

6×112 MW Birecik Hydroelectric Power Plant and Birecik Dam

The Birecik Dam and Hydroelectric Power Plant is located on the Euphrates river in the South Eastern part of Turkey. Birecik Dam and Hydroelectric Power Plant is located on the Euphrates river in the South Eastern part of Turkey. Dam crest is more than 2.5 km. long and consist of earth embankment dams on the left and right banks of the river, having a concrete gravity dam section in between, which integrates the spillway and the intake structure to the powerhouse. The dam height is 62.5 m. Power house is equipped with six Francis turbines with 112 MW each, with a total capacity of 672 MW. An annual electricity production of about 2.5 billion kWh is anticipated. In addition, the 56 km2 reservoir is planned to be used for irrigation of 70,000 hectares of farmland. The project is implemented on a “finance-built-operate-transfer” bases, with an operation period of 15 years.

This is the first major project in Turkey to be implemented on finance-built-operate-transfer basis.

TUPRAS Izmir Refinery – CCR and Isomerization Plants

The existing refinery is extended with two new units to increase the capacity for high-octane-fuel and to produce unleaded-fuel.

Besides CCR and Isomerization Units a new cooling tower, a flare unit, three storage tanks were supplied and connections of existing and new units are performed.

This turn-key project is executed by FWI (Italy) and GAMA Industry Consortium.

Ipek Paper Mill

Turn-key civil construction of a Paper Mill consisting of reel storage unit, workshop, boiler plant extension, infrastructural works, roads and storage areas is implemented.