The project mainly consists of the construction of an earthfill dam, installation of a total of 133,290 linear meters of steel and ductile iron water transmission pipe-lines and construction of two booster pumping stations in Built-Operate-Transfer basis.
Country: Turkey
GAMA performed construction, manufacturing and erection of 478 MW Marmara Ereğlisi Natural Gas Combined Cycle Power Plant.
Construction of Istanbul Metro Project 1st Phase – 1st Part, 3.4 km long Mecidiyeköy – 4. Levent line with 3 stations is implemented.
Manufacturing, construction and erection works of a Hydrogen Peroxide (H2O2), and Carbon Monoxide and Hydrogen plant.
Turnkey construction of 14.6 km heavy rail transit system, 7 km being underground with 12 passenger stations including an operation and maintenance center with parking facility.
GAMA – Guris Joint Venture (50%-50%) executed the detailed design, procurement, construction, test and commissioning of complete civil and building works – incluidng tunneling, building services and tunnel ventilation and installation of all electrical and mechanical subsystems.
The system is equipped with 108 vehicles operating in six-car trains of triplets with 90 second headway moving block automatic train control (ATC) system.
GAMA constructed detached housing (villas) complex within a 85,000 m2 area as a property development project. The project included 173 villas of 5 different types, shopping center, administrative and social facilities, swimming pool, sport fields, children play areas, infrastructure, sewage treatment plant , landscaping and beach facilities.
Turnkey design, supply and construction of a natural gas fired cogeneration plant, comprising two GE frame 6B gas turbine generators (39.5 MW capacity each) and two HRSG’s (each generating 80 tons/hr of medium pressure and 4 tons/hr of low pressure steam), including all auxiliary components are executed.
Turnkey construction of Kizilay Common Underground Station is undertaken by GAMA – Güriş Joint Venture.
Design and construction works of three level underground station building with 36,000 m2 of building area aree implemented by using top-down construction method.
Design, construction, manufacturing and complete mechanical and electrical erection of kiln precalcination unit.