Construction of Lassa Tire Factory and related buildings with a total construction area of 80,000 m2
Country: Turkey
Erection of two 30 MW steam generators, 30 MW turbo generator and 20 MW turbo blower.
Erection of the 150,000 tons/ year capacity soda ash plant.
GAMA installed the electrical equipment and instruments for the Synthetic Rubber Plant in Izmit-Turkey.
Erection of 37 km. long, 4″-44″ diameter pipeline for Izmir Aliaga Refinery.
Construction of 2 each 63 km, 5″ diameter Schedule 120 pipeline from Murgul to Hopa.
Construction and erection of 4×25 MW steam boilers and balance of plant.
GAMA constructed Units 1 & 2 as subcontractor to Babcock and Wilcox (U.S.A), and Units 3 & 4 under direct contract to the Cukurova Electricity Company.